Refurbishing in Westminster: conservation areas, listed buildings and consents

Refurbishment8 minute readReviewed 22 October 2026

Refurbishing a home in Westminster or Kensington and Chelsea means working inside one of the most protected townscapes in the world. The design matters, but so do the consents, and the order in which they are obtained. This guide sets out the permissions a central London project can need.

The setting

The City of Westminster has 56 conservation areas covering about 78% of the city, and more than 11,000 listed buildings and structures. In Kensington and Chelsea, about 70% of the borough lies within conservation areas. Mayfair is a single conservation area; Marylebone is covered by several, including the Portman Estate, Harley Street and Dorset Square conservation areas.

Our own office is a good example. 120 Baker Street is part of a Grade II listed terrace of town houses built by the Portman Estate in the late eighteenth century, so any alteration that affects its special character needs listed building consent.

Listed building consent

No one may demolish, alter or extend a listed building in any way that would affect its character as a building of special architectural or historic interest without listed building consent. The protection covers the interior as well as the exterior, and fixtures and later additions can be included. Carrying out such work without consent is a criminal offence, with a penalty of up to two years' imprisonment, and the council can require the work to be reversed.

Early advice from a heritage consultant, and where useful a pre application discussion with the council, usually saves time. Applications are judged on the significance of what would be lost or changed, so a careful assessment of the building comes first.

Planning permission and Article 4

Internal works to a flat do not usually need planning permission, but changes to the outside of a building in a conservation area often do, including windows, doors, roofs, railings and anything visible from the street. Article 4 directions remove some permitted development rights altogether. In Westminster, a citywide direction has removed permitted development rights for basements since 31 July 2016, and further directions restrict the conversion of commercial space to homes in parts of the Central Activities Zone and in town centres. Westminster's current plan is the City Plan 2019 to 2040, updated by a partial review adopted on 21 January 2026.

Basements

Both boroughs control basements closely.

  • Westminster generally allows no more than one storey below the lowest original floor, beneath no more than half of the garden, with an undeveloped margin, at least one metre of soil and a drainage layer over the top, and strict limits under the highway.
  • Kensington and Chelsea generally limits basements to a single storey under no more than half of each garden, with at least one metre of soil above, and does not allow excavation under a listed building.

Any basement scheme should be tested against the current policy wording before design work is commissioned.

Building Regulations and building safety

Most refurbishment needs Building Regulations approval, through the council's building control service or a registered building control approver. Since 1 October 2023, everyone who commissions, designs or carries out building work has defined duties to make sure it complies.

Higher risk buildings, those of at least 18 metres or seven storeys with at least two homes, follow a stricter regime. The Building Safety Regulator must approve work before it starts, within 12 weeks for a new building or 8 weeks for work to an existing one, and must issue a completion certificate before the building is occupied. The Regulator became a standalone body on 27 January 2026.

Party walls

The Party Wall etc. Act 1996 requires notice to be given to neighbours before work to a shared wall or structure, before building a new wall on the boundary, and before certain excavations near a neighbour's foundations. Where a neighbour does not consent, surveyors agree an award setting out how and when the work will be done. Notices should go out early, because the Act sets minimum notice periods before work can start.

The freeholder's consent

Most flats in central London are leasehold, and most leases require the landlord's written consent, usually a licence for alterations, before structural or significant works. Many buildings are owned by the great estates, which have their own standards for materials, plans and working hours. Their consent can take longer to obtain than planning permission, so it should be sought early.

Safety on site

The Construction (Design and Management) Regulations 2015 apply to all building work. A commercial client must make suitable arrangements for managing the project and, where more than one contractor is involved, appoint a principal designer and a principal contractor in writing. Where the client is an individual having work done on their own home, most of these duties pass to the contractors.

Doing things in the right order

  1. Survey the building and check the title, the lease and the planning history.
  2. Establish what is listed, what is protected and what the lease allows.
  3. Design with the consents in mind, then apply for planning and listed building consent.
  4. Obtain the freeholder's licence, serve party wall notices and secure Building Regulations approval.
  5. Tender and sign the building contract only when consents are in place.
  6. Keep every certificate and approval for the handover file, because a future buyer's solicitor will ask for them.

Important

This guide is general information about England, reviewed on 22 October 2026. It is not legal, tax or financial advice. Rules change; check the sources below before you act.